Adrian Dunkley
Jamaica · Infrastructure

Should Jamaica build an AI data centre?

I would start with a paid hosting and disaster recovery trial. Make a larger build earn its place through signed customer contracts, a grid study and a water plan that holds up through the dry season.

Build your own data centre ↗
Explore the campus
Tap a dot to see what the centre needs.
Hills and development along the coast of Montego Bay in St James, Jamaica
Montego Bay’s coast shows why flood and storm-surge screening belongs early in site selection. Photo by Trevor Cameron on Wikimedia Commons. CC BY 2.0. Resized and converted.

What would Jamaica sell?

Picture a Caribbean bank testing whether it can reopen after a hurricane. Its team needs a second copy of critical systems and a place to run them if its main site fails. A Jamaican data centre could sell that service to Caribbean customers alongside other workloads. Think of a hospital keeping its records available during a storm or a university renting the computing hours it needs to test a flood model. Read the World Bank’s analysis of Jamaica’s digital economy for the context behind those options.

On 15 November, Prime Minister Andrew Holness said the Government had approved a memorandum of understanding to explore AI infrastructure with investors. Public reporting gave no proposed size, site or timetable. The account of the Prime Minister’s remarks describes an exploratory step. I apply People First, Problem Second, AI Last here by starting with the worker who needs working systems after a storm and asking who will pay for the service that keeps them running.

What is a data centre?

A data centre is a building with computers, data storage and network equipment. It keeps them powered, connected and cool. A server is a computer that provides a service to another device. A chip is a small electronic circuit that processes instructions. A central processing unit (CPU) does general computing. A graphics processing unit (GPU) can run many similar calculations at once, which helps with some AI work. Training builds a model. Inference uses that model to do a job, such as reading a document. International Business Machines explains data centres and AI chips.

Start with demand you can count

Ask each prospective customer how much power it needs, where its data can be held, how quickly it must recover and what it will commit to pay. Test that demand with a paid hosting or recovery pilot and compare the result with leased capacity, regional cloud and keeping sensitive systems in-house. Cross-border transfers and data protection obligations need review for the actual service. See the market and data protection sources.

What the three sizes would ask of Jamaica

Jamaica’s 2022 census counted 2.77 million people. A facility can serve customers in all 14 parishes, but a specific neighbourhood hosts the power line, the water connection and the fibre trench. Ask who already depends on each one.

Planning ranges at full load
MeasureSmall localRegional hubLarge campus
Server capacity2 MW10 MW50 MW
Floor area5,000–25,000 sq ft25,000–100,000 sq ft100,000–300,000 sq ft
Equal floor area in example homes5–2525–100100–300
Peak facility power2.4–3.2 MW12–16 MW60–80 MW
Annual electricity equivalent in homes12,000–15,00058,000–77,000289,000–386,000
Evaporative cooling29,000–72,000 L/day144,000–360,000 L/day720,000–1.8m L/day
Annual evaporative cooling10.5–26.3 million litres52.6–131.4 million litres262.8–657 million litres
Cooling-water equivalent in three-person homes42–106211–5291,057–2,643
Peak construction workers15–5050–250200–800
Ongoing full-time equivalents8–2015–4025–80
Facility buildJ$2.9–4.8bnJ$14.4–24bnJ$72–120bn

How much space?

A regional hub could have the floor area of 25 to 100 example homes. Each example is a three-person household in a 1,000-square-foot home. I chose that size for the comparison. It is separate from the site acreage, which also has to fit tanks, electrical equipment, truck access and drainage. See the building benchmarks.

How much electricity?

A megawatt (MW) is one million watts. It measures power at a moment. A load of one megawatt running for one hour uses 1,000 kilowatt-hours (kWh). That second number measures energy, the units on your light bill. The regional hub has 10 megawatts of server capacity and needs 12 to 16 megawatts for the whole building at full load, including cooling and other equipment. United States Energy Information Administration, measuring electricity. See the facility power benchmark.

The Jamaica Observer, citing Jamaica Public Service Company, reported a 2025 peak of 696 MW. That tells you how the modelled loads compare with the system at its national peak. A utility study would tell you how much power a proposed site can take.

How much of Jamaica’s peak demand?

Bars show the high end on a 0–12% scale. Against the 696 MW 2025 peak, small is 0.3–0.5%, regional is 1.7–2.3% and large is 8.6–11.5%.

At full load all year, the regional case would use 105 to 140 million kilowatt-hours, the annual electricity of 58,000 to 77,000 residential accounts. The Jamaica Public Service Company’s 2025 report gives 1,817 kilowatt-hours per residential account. I use one account per comparison home. The report gives no breakdown for three-person homes.

How much water?

A litre (L) measures volume. Picture a one-litre bottle. A cubic metre holds 1,000 litres. A regional hub using evaporative cooling at full load could consume 144,000 to 360,000 litres a day, or 52.6 to 131.4 million litres a year. That matches the piped planning demand of 211 to 529 three-person homes. The Water Resources Authority uses 227 litres per person per day in its piped-service model. Three people at that rate use 681 litres a day.

The estimates use 0.6 to 1.5 litres per server kilowatt-hour. Withdrawal is how much water the site takes in. Consumption is how much fails to return to the local water system, including water that evaporates. A design that releases heat into the air can cut cooling water close to zero. Other on-site uses and water used to generate electricity need their own counts. Ask for the cooling plant’s water demand in a hot, dry week. See the cooling assumptions and examples.

How many jobs?

A regional build could have 50 to 250 workers on site at its peak. Once it opens, the scenario allows 15 to 40 full-time-equivalent roles, including contractor time. A full-time equivalent adds up hours into full-time workloads. Development work could include surveying and design. Operations could create work for electrical technicians, cooling specialists, network engineers and security teams.

In Virginia, industry representatives told the Joint Legislative Audit and Review Commission that a typical 250,000-square-foot facility could have about 50 full-time workers, roughly half contractors. The size and labour market differ from Jamaica. Use that evidence to check the distinction between peak builders and staff on shift, then ask a Jamaican contractor to cost both.

How to build it in Jamaica

  1. Test a paid recovery pilot over 30 days in existing capacity. Ask two prospective customers for their current recovery time. Run one restore on the test setup with its usual connection disabled. Record how long it took and whether the customer would pay to repeat the service.
  2. Ask for two comparable site quotations before you buy land. Check firm power with Jamaica Public Service Company, drought supply with the water provider and Water Resources Authority as relevant, and independent fibre with carriers. Commission flood, geotechnical, wind and access studies. Include the backup site in the same storm exercise.
  3. Confirm planning and environmental requirements with the relevant authorities before committing. For prescribed activities, the National Environment and Planning Agency administers environmental permits and licences. Address water abstraction and discharge, fire access, emergency power and data protection where applicable. Publish who funds upgrades.
  4. Build in modules. Fit out the first server hall, electrical plant, network and cooling system for contracted workloads. Test operation when one feed, fibre route or cooling component fails. Verify metering, failover and recovery with the customers before opening.
  5. Measure before expanding. Publish operating water, power and job figures and check them against the business case. Add capacity once customers and utilities can support it.

Three places to screen

Kingston and St Andrew for a small facility near existing hosts and customer teams. Caymanas and Portmore in St Catherine for industrial or technology plots, with flooding and storm surge screened plot by plot. Greater Montego Bay in St James for a separate western recovery site, if higher ground and independent utilities pencil out. A map helps a buyer rule out the wrong plot early. The shortlist still needs drainage, connection and land surveys at each address. A plot near an existing operator can save a site visit, but the engineer still needs a utility study to know the spare capacity. See the location references.

What it costs to build and run

Upfront cost and annual bills

The regional facility could cost J$14.4 to J$24 billion for the building and core systems. Before a developer buys land, get separate quotes for servers, fibre, the water connection and any new power lines or substation. A grid project could change both the budget and the launch date. See the construction benchmarks.

Sample annual costs for hybrid cooling at 65% average server load
Annual costSmall localRegional hubLarge campus
Electricity used16.2 million kWh80.9 million kWh404.3 million kWh
Electricity billJ$566 millionJ$2.83 billionJ$14.15 billion
Other operating cost allowanceJ$176 millionJ$878 millionJ$4.39 billion
Gross annual operating costJ$742 millionJ$3.71 billionJ$18.54 billion

I used a model price of J$35 per kilowatt-hour and 1.42 units of facility power for each unit used by servers. The allowance for staff, maintenance, fibre, water, security, insurance and backup fuel is 4% of a sample facility-and-site budget. Gross costs come before tenant power payments. Price replacement hardware, tax and financing separately. The site quote and tariff can change the result. See the financial inputs.

What customers could pay for

  • Disaster recovery for banks, insurers and government. Charge a monthly fee for protected systems, tested backups and a recovery-time commitment. This is the first service I would test with paying customers.
  • Private cloud, shared hosting and secure storage. Lease racks or reserved power to firms that bring their own servers. Sell storage by volume and managed services by contract.
  • Media delivery and local network services. Sell reserved capacity to carriers, broadcasters or streaming providers that want to serve nearby users.
  • AI for document reading, speech and research. Sell processing by request or reserved accelerator-hour. Ask universities and firms to price the jobs they can run on shared chips before buying a full room of them.

Track foreign sales, Jamaican payroll and local purchasing. Show tax revenue after concessions and public infrastructure costs. Those figures tell the public who receives the benefit. Customer use cases draw on the World Bank’s digital economy study and Jamaica’s existing recovery services.

For hosting, sales come from leased server power each month. For AI services and training, sales come from billed accelerator-hours. An accelerator is a chip that can carry out many calculations at once. One chip-hour means one paid hour on one chip. The operator buys the chips in the AI cases. I charge the model for replacing part of that equipment every four years. A tenant who supplies its own servers has a different bill and a different risk.

Cash over 15 years at 10 MW of servers

Cumulative cash after the initial facility and hardware cost and later hardware refresh. Jamaican dollars, before tax and debt.
Illustrative cases at 70% sold and 65% average server load
WorkloadBuild budgetAnnual salesCapital payback15-year discounted value

The model uses J$35 per kilowatt-hour as an editable energy-price assumption and a 12% discount rate. Hosting uses J$24,000 per leased kilowatt per month in the example. The rate draws on North American asking rents and is a Jamaican scenario assumption. Use actual quotes for equipment, power and leases. AI service prices, paid hours and accelerator counts are illustrative. The weakest part of the case is the number of paid computing hours. A buyer can test a higher electricity price today. Only customer contracts can show what customers are willing to pay over time. See the financial benchmarks.

Jones Lang LaSalle’s 2026 outlook forecasts a global average build cost of roughly J$1.8 billion per megawatt at the rounded exchange rate used here. Its benchmark covers the shell and core systems of a 50-megawatt air-cooled building. I would ask a local builder to price the project on its own scope before relying on that average.

Operating break-even answers whether sales cover running costs. Capital payback answers when cumulative cash first covers the build and intervening refresh costs. Return on investment here is cumulative net cash after those costs divided by the initial budget. Discounted value adjusts each year’s cash for time. Use these tests to ask different questions. An operator can cover its running costs and still spend years recovering the money it put into the building. An investor can recover the build cost eventually and still earn less than its required return. The model puts the full build cost at opening. It uses Jamaican dollars and leaves out the timing of construction payments, taxes, debt and resale value.

What could go wrong?

Grid, water and community risk

  • Power bills. If the operator needs a new substation or new generation, who pays? Ask for the tariff and an assessment of what happens when the project grows or its largest customer leaves.
  • Outages. Can the connection serve homes and the project when a major line goes down? What load can the centre reduce quickly? A national percentage cannot answer that.
  • Water. How much would the centre withdraw, how much would it consume, and does it have a dry-season alternative? Publish the cutback plan for times when households face restrictions.
  • Economic return. How much of the spending reaches Jamaican workers and suppliers? Which contracts would bring in export revenue, and what tax concessions or infrastructure contributions would the public carry?
  • Flood, hurricane and community risks. What happens to backup power, fibre and road access in the same storm? How will the operator manage noise, generator emissions and equipment disposal?

The International Energy Agency writes, “how costs are allocated in the electricity system is ultimately up to policymakers.” Residents should see the proposed cost before the decision. If you operate a factory on the same line, ask how the utility would serve both facilities after a fault. See the electricity analysis.

Cybersecurity and IT continuity

A centre can lose service because of an account takeover, a failed update or a cut fibre cable. Give staff only the access they need. Require multifactor sign-in, encryption and separate networks for tenants and equipment controls. Keep an isolated copy of backups and test the restore. Ask to see the time a recovery drill took and who notified customers. The Office of the Information Commissioner sets out relevant safeguards, audits and restoration practices.

Data sovereignty

Data sovereignty concerns the laws and authority that apply to data. Data residency is where the data sits. Ask where the main copy and backups are, which staff and suppliers can access them, who controls the encryption keys and how a customer can move its data out. Section 31 of Jamaica’s Data Protection Act, 2020 sets an adequate-protection standard for transfers of personal data outside Jamaica, with exceptions. Test the provider’s exit process before entrusting it with sensitive records.

Wind turbines on a ridge above green hills in Jamaica
Wind can contribute electricity. A project still needs a plan for serving load when it drops. Photo by Gwyneth Davidson on Wikimedia Commons. CC BY-SA 3.0. Resized and converted.

Build your version of the deal

Pick a parish, a customer and a cooling system. Watch the centre go up, check the water and power demands, then download your one-page report.

Play the AI Data Center Game ↗

Questions to put to an operator

How much can a bank learn from a recovery drill?

A bank can measure the minutes it takes to restore a copy, the point up to which records were recovered and whether the team could work when the normal line was down. Ask staff to record who made each decision and who could open the recovered systems.

Can the same site serve all 14 parishes?

Yes, provided users can reach the services they need. Have teams in different parishes test access over their normal connections. Ask the operator to trace two routes from the facility to its customers and show which roads, ducts or exchanges the two routes share.

What would a shared cooling-water contract say?

A contract should name the water source, the maximum withdrawal and how the operator measures consumption. It should specify who can order a cutback, what supply is protected first, how a neighbour can raise a problem and who pays for any separate storage.

When can the developer add a second hall?

Ask for signed customers that need the extra space, utility letters confirming added load and a procurement plan with local training roles. An expansion gate can also require the operator to publish its first-year water and electricity use so the new estimates start with measured data.

Sources and model inputs

For related work on Caribbean AI, see StarApple AI and the Caribbean AI Risk Management Council.