Research newsletter · Portmore, Jamaica

Who would buy time at a Portmore data centre?

Start with a paying customer. At a 10% annual return requirement, our model puts a new one-megawatt Portmore facility US$6.10 million below break-even in today’s dollars. A paid trial at an existing centre would show what buyers will pay before anyone commits to a building.

Adrian Dunkley and Nicholas Dunkley · Maestro AI Labs · 19 November 2026

Test your own numbers

What Portmore has proposed

On 17 November, St Catherine East Central MP Alando Terrelonge asked Parliament to make Portmore home to a technology park and AI data centres. Cabinet had already approved signing a memorandum to explore AI infrastructure in Jamaica. A site, a project budget and committed buyers are still open questions.

On 18 November, Information Minister Dana Morris Dixon said any project under the national exploration must avoid drawing power from the public grid or affecting Jamaica’s water systems. “It cannot be pulling from the grid,” she told reporters. A developer would need to show how the site keeps running during a power cut and where its water comes from during a drought.

Parliamentary proposal, reported 18 November · Cabinet briefing, 18 November

This time-lapse shows how a data centre could be built on the Portmore coastal plain, from survey stakes to equipment tests. It uses an illustrative site and layout. Download the silent film.

What customers would pay for

A bank could bring its own servers and pay for rack space and electricity. That service is called colocation. A business running an AI model could rent time on the operator’s graphics processing units, or GPUs. The operator pays to buy and replace those chips. Our model assigns three quarters of a 1 MW computing facility to colocation and the rest to GPU rental. We assume customers eventually pay for 75% of the capacity on offer. Financial figures use US dollars unless marked otherwise.

$18.80mInitial operator investment
$5.83mRevenue in a normal mature year
−$6.10mInvestor net present value

Once sales settle, the reference facility sells about 1.16 million GPU-hours a year and rents out 562.5 kW of rack capacity on average. Operating costs reach $2.87 million in a normal year after the first chip replacement. The simple return is 29.75% over 15 years, with payback in year 12. That calculation gives a dollar earned in year 12 the same weight as a dollar today. Apply the investor’s 10% annual return requirement and the project falls short. Net present value measures that shortfall in today’s dollars.

Jamaica already has buyers for these services. The Urban Development Corporation used Digicel’s Caymanas facility for off-site backups in 2011–12. eGov Jamaica reported full availability for its hosted services in 2024–25. The Passport, Immigration and Citizenship Agency also procured colocation. The records establish local use. A Portmore revenue forecast still needs customer orders.

UDC annual report, p. 11 · eGov Jamaica annual report, 2024–25 · PICA co-location procurement record

How far would prices or sales have to move?

Change one input at a time and the mixed facility breaks even at 90.6% paid use, $3.84 per GPU-hour or $330 per rack kilowatt per month. The table shows other ways to sell computing capacity at the same facility size. Each uses its own price and sales assumptions.

Operating caseAnnual revenue once sales settleNet present value
Rent rack space$3.20m−$9.88m
Domestic hosting$4.68m−$5.35m
Research computing$6.52m−$18.84m
Run AI models for overseas customers$11.42m−$1.84m
GPU rental only$14.03m$7.02m

Selling only GPU time clears the required return if the operator can restore its starting rental rate every time it buys new chips. Hold equipment purchases and paid use fixed, then let the rate fall 5% a year across the full period. The same facility’s value drops to −$7.30 million.

We ran 10,000 trials for the mixed facility. We varied customer demand, prices, construction costs, staffing and storm losses. The trials allow some changes to happen together. For example, weaker demand can put pressure on prices.

30.58%Trials that cleared the required return
−$6.27mMedian net present value
0.51%Trials meeting the return and ten-resident-job targets

The middle 80% of simulated investment values run from −$19.33 million to +$9.73 million. Those results show how the model responds when assumptions change. Investors still need local bills, bids and contracts to narrow the range.

Where the simulated returns landed

-36 to -33 million dollars: 7 trials-33 to -30 million dollars: 16 trials-30 to -27 million dollars: 80 trials-27 to -24 million dollars: 219 trials-24 to -21 million dollars: 369 trials-21 to -18 million dollars: 606 trials-18 to -15 million dollars: 804 trials-15 to -12 million dollars: 893 trials-12 to -9 million dollars: 1033 trials-9 to -6 million dollars: 1066 trials-6 to -3 million dollars: 959 trials-3 to 0 million dollars: 890 trials0 to 3 million dollars: 818 trials3 to 6 million dollars: 629 trials6 to 9 million dollars: 521 trials9 to 12 million dollars: 372 trials12 to 15 million dollars: 298 trials15 to 18 million dollars: 194 trials18 to 21 million dollars: 108 trials21 to 24 million dollars: 70 trials24 to 27 million dollars: 37 trials27 to 30 million dollars: 11 trialsHighest bar: 1,066 trials $0$-36m$30m
Each bar counts trials in a US$3 million band. The orange line marks the point where the investment meets the required return.

Stress on the reference caseNet present value
Higher fuel cost−$8.24m
Construction overrun−$13.74m
30-day flood outage−$7.89m
Demand falls as fuel and build costs rise, with heat and flooding−$29.58m
90% paid use, US$3.50/GPU-hour, US$225/kW-month and 5% lower construction costs$6.50m

What it takes to keep the servers cool

On a hot day at full load, the site needs 1.50 MW of power that it can rely on. The model uses three dedicated gas engines. Two can meet that load while the third is out of service. The supplier puts up $3.71 million and charges the operator $566,006 a year to keep the plant available. With fuel and operating costs, power comes to $0.226 per kilowatt-hour in a normal year after sales settle.

Jamaica’s large commercial grid tariff, Rate 50, averaged J$40.83 per kilowatt-hour in 2025. Use that figure for context. A Portmore developer needs a quote for a dedicated supply that covers fuel, maintenance and backup during a storm.

Jamaica Energy Statistics 2025, pp. 15 and 18

Cooling designElectricity per yearWater per yearNet present value
Dry7.46 GWh477 m³−$6.10m
Hybrid6.93 GWh2,379 m³−$6.26m
Evaporative6.51 GWh8,745 m³−$5.56m

How much water does cooling choice add?

Dry477 m³
Hybrid2,379 m³
Evaporative8,745 m³
Total annual water in a normal mature year. Each design serves the same workload.

Dry cooling sends heat into the air. An evaporative tower uses water to remove heat, so it uses less electricity in this model. A hybrid system adds water when air temperatures rise. All three estimates include water for staff, cooling and the power plant.

The Bernard Lodge rainfall record shows why the month matters. With a 1,000 m² roof that collects 80% of the rain, historical averages would yield 656 m³ a year and 16.8 m³ in January. A developer needs storage and a water source that still delivers in a dry spell.

Bernard Lodge rainfall record, Table 15

In the model, the engines emit about 4,158 tonnes of carbon dioxide in a normal year after sales settle. The estimate covers fuel burned at the site. Solar panels and batteries could cut fuel use. The developer still needs enough stored energy or fuel to get through a storm.

Who gets the jobs and what happens in a storm?

Greater Portmore had 57,927 residents in the 2022 census. Bridgeport had 10,261. A hiring plan needs to show where the operator will recruit electricians, cooling technicians, security staff and network engineers.

STATIN community census

Across all shifts, the model budgets work equal to 10.25 full-time jobs. If Portmore residents fill 70% of those hours, they get the equivalent of 7.2 full-time jobs. A developer who promises ten resident jobs at that share would need about 15 full-time posts. Construction accounts for another 37.4 resident job-years. One job-year is one person working full time for a year.

The operator would pay residents $229,600 in a normal year. The model counts 35% as additional wages because workers can earn some of that income elsewhere. It adds an estimate of what local suppliers retain from project spending. A separate fiscal review would need to calculate local taxes and any public subsidy.

Greater Portmore recorded 224.5 mm of rain during Hurricane Melissa in October 2025. Earlier surveys documented flood access problems in Westmeade and Bridgeport. A developer can raise the server hall and still lose the road that brings fuel or the ducts that carry both fibre lines.

In our seven-day stress test, a fuel tank sized for average use left 108.9 megawatt-hours of demand unmet at full hot-day load. We assumed one engine was down and neither solar power nor new fuel arrived. Check roads, drains and fibre routes alongside the building footprint.

National Hurricane Center, Hurricane Melissa, Table 3 · Mines and Geology Division, Portmore flood study

Put the first contract ahead of construction

Run a paid trial with an existing operator. Measure how fast the service responds, how often it stays available and how long it takes to recover after a failure. Then ask the customer to put a minimum purchase and price in writing.

Over 15 years, the model puts buying the same service at $41.13 million in today’s dollars, about $3.40 million less than building. That assumes $3 per GPU-hour and $330 per rack kilowatt per month with power included. Get quotes on the same terms for both options. If a site makes the shortlist, commission a flood and wind study and publish the proposed jobs, shifts and training budget before making a public contribution.

Enter a customer or supplier offer

Assumptions, evidence and papers

These are the inputs for the mixed reference case. Replace the price and volume assumptions with written bids and customer commitments as they come in.

InputReference assumption
Computing capacity1 MW. Colocation customers supply their IT equipment. The operator buys GPU equipment.
ConstructionUS$12m per megawatt of computing capacity before site work and protection. Drainage and wind protection add 6% to the facility allowance.
SalesUS$200 per occupied rack kW per month, plus 90% power-cost recovery on the tenant share. US$3 per billable GPU-hour at the start of each five-year cycle.
Capital and time15 operating years at a 10% annual discount rate after inflation. The operator replaces chips in years 5 and 10. The model excludes resale, income tax and debt.
Power and waterDedicated firm supply. US$0.15 per kWh of engine energy plus a capacity charge. Water at US$7 per cubic metre.
Hiring70% resident operating hours. US$32,000 per full-time year. Construction job-years use a separate labour share.
HazardStarts with an assumed 8% chance of a disruption in year one and increases it by 2% of the starting rate each year. A parcel survey and insurance quote would supply site-specific inputs.
Simulation10,000 draws. Seed 41926. BootLoops checked 46 quoted values against the model output and caught three deliberately changed values in a separate test. Resampling estimates how much the trial summaries can vary from one run to another.